Skip to the page's content
Back to Newsroom

New roundabout junction at Shepperton

Our team have recently completed the construction of a new roundabout at the junction of Studios Road, New Road and Squires Bridge Road in Shepperton.

Posted by Careys

Thursday 6th March 2025

Share via

New roundabout junction at Shepperton

This new roundabout improves the flow of traffic through this junction, making it safer than the previous junction. Our scope of works included:

- Break out and removal of the existing carriageway and replacing with
new
- New kerb lines and drainage
- Installation of a new signalised pedestrian crossing
- Installation of new signage including illuminated chevron
- New fencing to the works boundary
- Utility diversions and installation of new chambers while keeping the
network live for customers
- Installation of two large soakaways
- Soft Landscaping
- Liaison with the adjacent school and neighbours

The works were completed ahead of programme.

Posted by Careys

Thursday 6th March 2025

Share via